Geelong Bypass

Project data

Location: Geelong, Australia

Section one of the Geelong Bypass project involved a new bypass from Corio to the Midland Highway. 

  • Consists of two abutments each measuring 36 metres long by 9.8 metres high

Requirements

  • The abutment should be done in one pour full height
  • Short amount of time
  • Sufficent equipment to form up one complete abutment and one face of the other abutment

Customer

Abigroup Contractors P/L

Benefit to customer

  • Erect the system in a short amount of time
  • A huge time saving

PERI solution

  • The TRIO wall formwork system and the DW20 tie rods for the bridge abutment.
  • Once the first abutment was poured, the assembled shutters from this abutment were craned straight into position on the second abutment. 